PDF Only
$35.00 Free Updates Upto 90 Days
- H19-311 Dumps PDF
- 225 Questions
- Updated On November 18, 2024
PDF + Test Engine
$60.00 Free Updates Upto 90 Days
- H19-311 Question Answers
- 225 Questions
- Updated On November 18, 2024
Test Engine
$50.00 Free Updates Upto 90 Days
- H19-311 Practice Questions
- 225 Questions
- Updated On November 18, 2024
How to pass Huawei H19-311 exam with the help of dumps?
DumpsPool provides you the finest quality resources you’ve been looking for to no avail. So, it's due time you stop stressing and get ready for the exam. Our Online Test Engine provides you with the guidance you need to pass the certification exam. We guarantee top-grade results because we know we’ve covered each topic in a precise and understandable manner. Our expert team prepared the latest Huawei H19-311 Dumps to satisfy your need for training. Plus, they are in two different formats: Dumps PDF and Online Test Engine.
How Do I Know Huawei H19-311 Dumps are Worth it?
Did we mention our latest H19-311 Dumps PDF is also available as Online Test Engine? And that’s just the point where things start to take root. Of all the amazing features you are offered here at DumpsPool, the money-back guarantee has to be the best one. Now that you know you don’t have to worry about the payments. Let us explore all other reasons you would want to buy from us. Other than affordable Real Exam Dumps, you are offered three-month free updates.
You can easily scroll through our large catalog of certification exams. And, pick any exam to start your training. That’s right, DumpsPool isn’t limited to just Huawei Exams. We trust our customers need the support of an authentic and reliable resource. So, we made sure there is never any outdated content in our study resources. Our expert team makes sure everything is up to the mark by keeping an eye on every single update. Our main concern and focus are that you understand the real exam format. So, you can pass the exam in an easier way!
IT Students Are Using our Huawei Certified Pre-sales Associate- Data Center Facility Dumps Worldwide!
It is a well-established fact that certification exams can’t be conquered without some help from experts. The point of using Huawei Certified Pre-sales Associate- Data Center Facility Practice Question Answers is exactly that. You are constantly surrounded by IT experts who’ve been through you are about to and know better. The 24/7 customer service of DumpsPool ensures you are in touch with these experts whenever needed. Our 100% success rate and validity around the world, make us the most trusted resource candidates use. The updated Dumps PDF helps you pass the exam on the first attempt. And, with the money-back guarantee, you feel safe buying from us. You can claim your return on not passing the exam.
How to Get H19-311 Real Exam Dumps?
Getting access to the real exam dumps is as easy as pressing a button, literally! There are various resources available online, but the majority of them sell scams or copied content. So, if you are going to attempt the H19-311 exam, you need to be sure you are buying the right kind of Dumps. All the Dumps PDF available on DumpsPool are as unique and the latest as they can be. Plus, our Practice Question Answers are tested and approved by professionals. Making it the top authentic resource available on the internet. Our expert has made sure the Online Test Engine is free from outdated & fake content, repeated questions, and false plus indefinite information, etc. We make every penny count, and you leave our platform fully satisfied!
Frequently Asked Questions
Question # 1
Which of the following is not the certifications obtained by the UPS2000-G series? ()
A. Enhanced Capital Allowance (ECA) tax allowance
B. Energy Star certification
C. Green Sites award
D. CE certification
Question # 2
For two UPS5000-E (50 kA power module) 150 kVA with 2+0 rack redundancy, a () general input switch is required for the general input power distribution cabinet.
A. 250 A
B. 320 A
C. 500 A
D. 630 A
Question # 3
The FusionModule500 license is free for up to 50 sites, but is charged for more than 50 sites.
A. TRUE
B. FALSE
Question # 4
The UPS5000-A features wide voltage and frequency input range. It can be used in severe grid environments and extend the battery service life. What's the maximum input voltage range of the UPS5000-A?
A. 138-85 V
B. 305-85 V
C. 240-80 V
Question # 5
The UPS5000-E (25-75 kVA) can be wall-mounted.
A. TRUE
B. FALSE
Question # 6
As the construction cost of the equipment room is high, reducing the floor area can efficiently save investment for clients. The floor area of a UPS5000-A-500K is ().
A. 1.02 m2
B. 2m2
C. 0.51 m2
Question # 7
The efficiency of the UPS5000-E (25-75 kVA) power module is 96%.
A. TRUE
B. FALSE
Question # 8
Which of the following elements will affect the application of HVDC in the equipment room? (Multiple Choice)
A. The standard is not complete, and multiple 240 V/336 V systems exist.
B. Not all loads can use the DC power supply directly,
C. The cost of DC circuit breaker components is high.
D. The efficiency is low.
Question # 9
Which of the following is the maintenance bypass implementation mode of the UPS2000-G series (6 kVA to 20 kVA)? ()
A. The UPS2000-G provides a built-in maintenance bypass.
B. A PDU is configured to support a maintenance bypass.
C. Maintenance bypass is unsupported.
Question # 10
The bypass module of the UPS5000-E-200K (50 kVA power module) is the same as that of the UPS5000-E-300K.
A. TRUE
B. FALSE
Question # 11
How many batteries does the UPS2000-G series (15 kVA to 20 kVA) support? () (Multiple Choice)
A. 28
B. 32
C. 36
D. 40
Question # 12
Which of the following statements are correct about the UPS5OO0-A-400/500K usability? (Multiple Choice)
A. The parallel board is configured.
B. The UPS floor area is only 1.02 m2.
C. The number of batteries is adjustable.
D. Smart battery management is supported.
Question # 13
Which of the following elements shall be considered when configuring a UPS? (Multiple Choice)
A. UPS model, capacity, and parallel system mode
B. Battery brand and capacity
C. Brand and model of the AC and DC cables
D. Configuration of the battery rack and battery switch box
Question # 14
If the total current of a battery string is 1000 A and three battery strings are configured, the most economic cable configuration between the UPS and the main switch box is ():
A. 120 mm2 (382 A) x 3
B. 150 mm2 (441 A) x 3
C. 185 mm2 (506 A) x 3
D. 240 mm2 (599 A) x 3
Question # 15
The output capacity of a single UPS is calculated on actual power when the actual load power is used for UPS configuration.
A. TRUE
B. FALSE
Question # 16
Conformal coating can effectively reduce the failure rate of the UPS in severe conditions/ including salt mist, dust, and high temperature and humidity, which ensures its service life in severe conditions.
A. TRUE
B. FALSE
Question # 17
The operating temperature range of the FusionModule800 is -20°C to +45°C, and that for the Fusion Mod ule500 is 0°C to 40°C.
A. TRUE
B. FALSE
Question # 18
Which of the following is not a configuration option of the 20-kVA UPS2000-G? ()
A. 4+0
B. 3+1
C. Dual-bus system
D. Battery string sharing
Question # 19
Which of the following UPS models support bypass hot-swap? (Multiple Choice)
A. UPS5000-E
B. UPS5000-A
C. APM series
D. PX250 series
Question # 20
According which of the following statements can you determine that the battery is faulty? (Multiple Choice)
A. The voltage increase of a battery is faster than the other batteries.
B. The temperature of the battery string during discharge is 2°C higher than the surrounding ambient temperature.
C. A battery suffers from obvious bulge and leakage.
D. The voltage drop of a battery is obviously faster than the other batteries.
Question # 21
The bypass module in the UPS5000-E-200K is the same as that in the UPS5000-E-400K.
A. TRUE
B. FALSE
Question # 22
Which of the following are the optional components for the UPS2000-G series (6 kVA to 20 kVA)? () (Multiple Choice)
A. Temperature and humidity sensor
B. Battery temperature sensor
C. Transformer
D. PDU
Question # 23
The Fusion Mod ule500 adopts free cooling.
A. TRUE
B. FALSE
Question # 24
Which of the following problems shall be considered when selecting the UPS cable? (Multiple Choice)
A. Rated current of the UPS
B. Rated operating voltage and insulating voltage of the power cable
C. Voltage drop of the power cable in the route
D. Number of the parallel cables
Question # 25
Which of the following are the highlights of the UPS2000-G series (6 kVA to 20 kVA)? () (Multiple Choice)
A. Reliable
B. Efficient
C. Simple
Question # 26
Which of the following models has the widest input voltage range and is applicable to severe power grids?
A. UPS5000-A
B. Emerson NXP
C. Eaton 9395
D. APC Galaxy7000
Question # 27
When using a UPS5000-E (50 kVA power module) with the actual load of 160 kW, 1+1 rack redundancy, and single UPS backup solution, each rack uses three battery strings, each battery string consists of 40 batteries, and the main switch box capacity is ().
A. 250A
B. 320 A
C. 500 A
D. 630 A
Question # 28
Do the aisles of the FusionModule800 have skylights? ()
A. Yes
B. No
Question # 29
In SCT, how many years is the longest lifetime for the spare part we could supply?
A. 2
B. 3
C. 4
D. 5
Question # 30
What is the maximum capacity of the UPS5000-E power module?
A. 20 kVA
B. 30 kVA
C. 40 kVA
D. 50 kVA
Question # 31
The optional components and features in the typical configuration solution of the FusionModule800 include ().
A. Temperature and humidity sensor, door status sensor, water sensor, smoke sensor, and
mobile app
B. Smoke sensor, door status sensor, water sensor, alarm notification over short
messages, and Huawei tablet
C. Door magnetic switch, Water leakage, Video system. Power backup system, iBattery,
Mobile APP (remote), Emergency fans
Question # 32
According to related standards and regulations, the AC cable voltage drop must be within 3%. You are advised to control the AC cable voltage drop within () when designing the UPS system.
A. 0.01
B. 0.02
C. 0.03
D. 0.05
Question # 33
Which of the following countries can the UPS5000-E (25-125 kVA) be sold to? (Multiple Choice)
A. China and Asian-Pacific region
B. Middle East and North Africa
C. The Commonwealth of the Independent States and Europe
D. North America
Question # 34
The Fusion Mod ule500 and FusionModule800 must have unified network management software configured for remote WebUI monitoring.
A. TRUE
B. FALSE
Question # 35
What UPS configuration method does the Fusion Mod ule800 support? ()
A. N/2N
B. N/N+1
C. N/N+1/2N
Question # 36
Which of the following products can be quoted in a configurator? (Multiple Choice)
A. UPS2000-G
B. UPS5000-E
C. FusionModule2000
D. UPS8000
Question # 37
Which of the following actions does the UPS2000-A take to deal with excessive operating temperatures?
A. Switch to bypass mode.
B. Switch to battery mode.
C. Stop output and power off loads.
D. No action is taken.
Question # 38
The UPS5000-E is an efficient UPS. Which of the following statements are correct? (Multiple Choice)
A. The efficiency can be up to 96%.
B. The efficiency can be up to 95% at 20% loads.
C. The efficiency can be up to 94% at 20% loads.
D. The efficiency can be up to 96% at 40% loads.
Question # 39
Which of the following are the functions of the SCT configurator? () (Multiple Choice)
A. Display product cost data
B. Provide quick overview of Huawei products
C. Quick solution configuration
D. Simple quotation creation
Question # 40
Which of the following statements are incorrect about the cable design? (Multiple Choice)
A. An unlimited number of power cables can be used in parallel when the current is high.
B. There is no need to derate because the UPS cable is designed based on the rated
current.
C. The UPS cable needs to consider the wiring capability of the UPS system terminal.
D. Controlling the UPS AC cable voltage drop within 5% can satisfy the design requirements.
Question # 41
The UPS2000-G supports low voltage disconnection. When overload occurs, secondary loads are closed to remove the overload and ensure desired power supply quality. When a power outage occurs, secondary loads are also closed to prolong the backup time for important loads.
A. TRUE
B. FALSE
Question # 42
Are the air conditioners of the Fusion Mod ule800 connected to the back end of UPSs? ()
A. Yes
B. No
Question # 43
Which of the following is the battery type for the UPS2000-G? ( )
A. VRLA
B. Lithium ion battery
C. Ni-Cd battery
D. Flywheel
Question # 44
The standard protection level of the UPS5000-A is ( ).
A. IP22
B. IP21
C. IP20
Question # 45
If the total current of a battery string is 1,000 A and three battery strings are configured, the most economic cable configuration between the main switch box and the branch switch box is ():
A. 95 mm2 (328 A) x2
B. 120 mm2 (382 A) x 2
C. 150 mm2 (441 A) x 2
D. 185 mm2 (506 A) x 1